Why in News: The Union Cabinet approved the Green Energy Corridor Phase-III (GEC-III) scheme on 30 September 2026 with an outlay of ₹1,86,405 crore — ₹1,36,378 crore for strengthening intra-state transmission systems and ₹50,000 crore for 50 GWh of battery energy storage. It aims to evacuate up to 135 GW of renewable energy by 2032–33, with central financial support of about ₹54,082 crore. It is the first phase of the programme to include dedicated storage.
Key Features
- Intra-State Transmission System (InSTS): new lines and substations so that solar and wind power from resource-rich districts can reach consumers.
- Battery Energy Storage Systems (BESS): 50 GWh at generator ends, congested nodes and load centres — to manage intermittency, evening peaks and grid congestion.
- Implementation by State transmission utilities with central grants; completion by 2032–33.
Why Transmission Is the Bottleneck
- India’s non-fossil capacity crossed 50% of installed capacity in 2025, but curtailment and delayed evacuation idle many projects.
- Renewable energy is concentrated in Rajasthan, Gujarat, Karnataka, Tamil Nadu and Ladakh, far from demand centres.
- Solar output peaks at midday while demand peaks in the evening — storage shifts energy across hours.
- Land acquisition and right-of-way delays slow lines.
Significance
- Supports the target of 500 GW non-fossil capacity by 2030 and net-zero by 2070.
- Boosts domestic battery manufacturing linked to the PLI scheme for Advanced Chemistry Cells and viability-gap funding for BESS.
- Reduces reliance on coal for peak demand.
Concerns
- Battery supply chains depend on imported lithium and cells, largely from China.
- Financial health of State utilities (DISCOMs) affects implementation.
- Safety, recycling and end-of-life management of batteries.
Static Background — Grid and Renewable Energy
- GEC Phase-I (from 2015): intra-state transmission in eight renewable-rich States — Tamil Nadu, Rajasthan, Karnataka, Andhra Pradesh, Maharashtra, Gujarat, Himachal Pradesh and Madhya Pradesh — with KfW (Germany) support; Phase-II (approved 2022) covers seven States for about 20 GW.
- National grid: “One Nation, One Grid, One Frequency” achieved in December 2013 when the southern grid was synchronised; managed by Grid Controller of India (Grid-India).
- Inter-State Transmission System (ISTS) charges are waived for renewable projects commissioned till mid-2025 (phased out after).
- India’s NDC (2022 update): 50% of installed capacity from non-fossil sources by 2030; 45% reduction in emissions intensity of GDP from 2005 levels.
- Pumped storage and batteries are the two main storage technologies; the Central Electricity Authority projects large storage needs by 2032.
| Phase | Approved | Focus |
|---|---|---|
| GEC-I | 2015 | Eight States’ intra-state lines (with KfW) |
| GEC-II | 2022 | Seven States, about 20 GW |
| GEC-III | 2026 | 135 GW evacuation + 50 GWh BESS |
Exam Angle — Prelims & Mains
- UPSC PYQ Link: Prelims has asked about the “Green Energy Corridor” and India’s renewable targets; Mains GS-3 on grid integration of renewables.
- Practice Mains Question (GS Paper 3, 15 marks, 250 words): “India’s energy transition is now a transmission and storage challenge more than a generation challenge.” Discuss with reference to the Green Energy Corridor Phase-III.
- Prelims Angle: phases, States covered and the storage component.
- Practice Prelims MCQ 1: Consider the following statements about the Green Energy Corridor programme:1. It focuses on transmission infrastructure for evacuating renewable power.2. Phase-III is the first phase to include a dedicated battery energy storage component.3. It is implemented only by the Power Grid Corporation through inter-State lines.Which of the statements given above are correct?(A) 1 and 2 only(B) 2 and 3 only(C) 1 and 3 only(D) 1, 2 and 3
Show answer
Answer: (A) 1 and 2 only — Statement 1 is CORRECT and Statement 2 is CORRECT. Statement 3 is INCORRECT — Phases I to III mainly strengthen intra-State systems through State transmission utilities. - Practice Prelims MCQ 2: India’s national grid became “One Nation, One Grid, One Frequency” when which regional grid was synchronised with the rest in 2013?(A) Northern(B) Eastern(C) North-Eastern(D) Southern
Show answer
Answer: (D) — The Southern grid was synchronised in December 2013, completing the single national grid.
- Practice Prelims MCQ 1: Consider the following statements about the Green Energy Corridor programme: