Case study: Land needed for mining, dams and other large-scale projects is acquired mostly from Adivasis, hill dwellers and rural communities.
Set out the ethical principles and method you would use, then list concrete policy elements, so the answer works as an outline for an actual policy.
Common trap: Most answers list generic schemes. A top answer begins from distributive justice, builds on (rather than ignores) the RFCTLARR Act, 2013, and adds what the Act lacks: benefit sharing, livelihood restoration and long-term monitoring.
SyllabusCase Studies on above issues. (Public/Civil service values and Ethics in Public administration: ethical concerns and dilemmas in government and private institutions; laws, rules, regulations and conscience as sources of ethical guidance; accountability and ethical governance; ethical issues in international relations and funding; corporate governance.)
The case
Land needed for mining, dams and other large-scale projects is acquired mostly from Adivasis, hill dwellers and rural communities. The displaced persons are paid monetary compensation as per the legal provisions. However, the payment is often tardy. In any case, it cannot sustain the displaced families for long. These people do not possess marketable skills to engage in some other occupation. They end up as low paid migrant labourers. Moreover, their traditional ways of community living are destroyed. Thus, the benefits of development go to industries, industrialists and urban communities whereas the costs are passed on to these poor helpless people. This unjust distribution of costs and benefits is unethical. Suppose you have been entrusted with the task of drafting a better compensation-cum-rehabilitation policy for such displaced persons, how would you approach the problem and what would be the main elements of your suggested policy?
Model answer
20 marks · 250-word limitThe Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, in force since 1 January 2014, already moved from cash-only compensation to rehabilitation as a right. A better policy must go further: make the displaced partners in development, so that those who bear its costs also share its benefits.
- Minimise displacement at project design
- Social Impact Assessment and free, prior consent
- Fair compensation paid before possession
- Land, housing, skills and jobs
- Share in project benefits
- Independent monitoring and grievance redress
Approach to the problem
- Justice as the lens: Rawls' difference principle suggests that inequalities are fair only if they benefit the least advantaged; displacement that leaves Adivasis poorer fails this test.
- Rights, not charity: Article 21 includes the right to livelihood (Olga Tellis, 1985), and the Fifth Schedule, PESA 1996 and the Forest Rights Act, 2006 give tribal communities and gram sabhas a say over their land and forests.
- Participation: The Niyamgiri case (Orissa Mining Corporation v MoEF, 2013), where gram sabhas decided on the bauxite project, shows that affected people must be decision-makers, not just recipients.
- Learn from experience: Long-running resettlement disputes in projects such as Sardar Sarovar show the cost of tardy, cash-only and top-down rehabilitation.
Main elements of the suggested policy
| Element | What it would provide |
|---|---|
| Least displacement | Examine alternative sites and designs; acquire only the minimum land; avoid multi-cropped land and Scheduled Areas where possible |
| Prior assessment and consent | Mandatory Social Impact Assessment, as under the 2013 Act; consent of affected families and gram sabha approval in Scheduled Areas |
| Fair and timely compensation | Market value with the 2013 Act's multiplier and solatium, paid before possession, with interest for delay |
| Land for land | Land in the same area for tribal and farming families, keeping communities and kin together |
| Livelihood restoration | Skill training linked to the project's own jobs, a job or annuity option per family, and support for cooperatives and enterprises |
| Benefit sharing | Share of project revenue or equity, community funds on the lines of District Mineral Foundations, and local hiring |
| Community and culture | Resettlement as villages, with schools, health centres, places of worship and common land rebuilt before shifting |
| Special care | Extra support for women, the elderly, landless labourers and forest-dependent families who hold no title |
| Accountability | Independent monitoring, social audits, a time-bound grievance authority, and return of unused land |
Making it work
- Rehabilitation before displacement: No family should be moved until the new site, livelihood and compensation are ready; the 2013 Act already ties possession to payment.
- Single-window and transparency: Publish entitlements, lists of affected families and payment status in local languages, and pay directly into bank accounts.
- Long-term tracking: Follow families for at least a generation, measuring income, health and children's schooling against their position before displacement.
A just policy measures success not by how quickly land is acquired but by whether displaced families are better off years later. When the people who give up their land become stakeholders in the project, development becomes both faster and fairer.
Read more — sources
- OfficialRight to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
- OfficialPanchayats (Extension to the Scheduled Areas) Act, 1996; Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006
- OfficialOrissa Mining Corporation v Ministry of Environment and Forests, Supreme Court, 2013
- BookJohn Rawls, A Theory of Justice (1971)
Related questions from earlier years
More from GS Paper 4 (Ethics) 2016
Model answer by the EdiShorts editorial team. It is one well-argued treatment of the question, written to the official word limit — not an official UPSC answer key.