UPSC Mains 2013GS Paper 3Q11 · 10 marksEconomyModel answer

Write a note on India's green energy corridor to alleviate the problem of conventional energy.

DirectiveWrite a note
Marks10
Word limit200
PaperGS Paper 3
What the examiner wants

Explain what the green energy corridor is, why it is needed, its main components and how it helps reduce dependence on conventional power, with its challenges.

Common trap: Candidates often describe solar and wind in general. A top note focuses on transmission: the PowerGrid report of 2012, intra-state and inter-state lines in renewable-rich states, Renewable Energy Management Centres for forecasting, and the problem of infirm power, linking it to coal shortages and the 2012 grid failure.

SyllabusInfrastructure: Energy, Ports, Roads, Airports, Railways etc.

Model answer

10 marks · 200-word limit

The green energy corridor is a planned network of transmission lines, substations and control systems to carry electricity from renewable-rich regions to demand centres and the national grid. It was conceived in the Power Grid Corporation of India's 2012 report, because renewable capacity was growing faster than the grid's ability to absorb it.

  1. Wind and solar parks in RE-rich states
  2. Intra-state transmission strengthening
  3. Inter-state high-capacity lines
  4. Renewable Energy Management Centres
  5. National grid and load centres
  6. Less coal and imported fuel used
How the green energy corridor moves clean power

Why it is needed

  • Concentrated resources: Wind and solar potential is concentrated in Tamil Nadu, Gujarat, Rajasthan, Karnataka, Maharashtra and Andhra Pradesh, far from many load centres.
  • Grid constraints: Wind generators in Tamil Nadu were often backed down for lack of evacuation capacity, wasting clean power.
  • Infirm power: Wind and solar output varies with weather; without balancing and forecasting, large injections threaten grid stability, a concern sharpened by the July 2012 northern grid failure.
  • Targets: The National Solar Mission aims at 20,000 MW of grid solar by 2022, and states face renewable purchase obligations.

Main components

  • Transmission: Intra-state networks in renewable-rich states and inter-state corridors linking them to the national grid.
  • Control: Renewable Energy Management Centres with forecasting and real-time scheduling linked to load dispatch centres.
  • Balancing: Flexible hydro and gas generation, reactive power support and, in time, storage.
  • Finance: Funding from the Centre, states and international partners, including German development cooperation.

How it eases the conventional energy problem

  • Energy security: Reduces dependence on scarce domestic coal and costly imported coal, oil and gas.
  • Climate: Cuts emissions in line with the National Action Plan on Climate Change.
  • Challenges: High cost, land acquisition for lines, weak finances of state utilities and inter-state cost-sharing disputes.

Without transmission, renewable capacity is stranded. The green energy corridor turns renewables from a marginal supplement into a reliable part of India's power supply, provided forecasting, balancing power and state utility finances improve alongside.

Answer length. This model answer runs to about 277 words so that every relevant angle is covered. In the exam, write to the 200-word limit: keep the opening, the strongest one or two points under each heading, the diagram and the conclusion.

Read more — sources

  • ReportPower Grid Corporation of India, Report on Green Energy Corridors: Transmission Plan for Envisaged Renewable Capacity (July 2012)
  • OfficialMinistry of New and Renewable Energy, Jawaharlal Nehru National Solar Mission — Mission Document (2010)
  • OfficialNational Action Plan on Climate Change (2008)

More from GS Paper 3 2013

Q1·10 marks·200 words·Economy
With a consideration towards the strategy of inclusive growth, the new Companies Bill, 2013 has indirectly made CSR a mandatory obligation. Discuss the challenges expected in its implementation in right earnest. Also discuss other provisions in the Bill and…
The Companies Bill, 2013 (passed by Parliament in August 2013, replacing the Companies Act, 1956) made India the first major economy to legislate corporate social…
Read the model answer →
Q2·10 marks·200 words·Economy
What were the reasons for the introduction of Fiscal Responsibility and Budget Management (FRBM) Act, 2003? Discuss critically its salient features and their effectiveness.
The FRBM Act, 2003 was India's first statutory fiscal rule. It aimed to bind the Union government to a time-bound path of lower deficits and debt, with transparency,…
Read the model answer →
Q3·10 marks·200 words·Economy
What is the meaning of the term 'tax expenditure'? Taking housing sector as an example, discuss how it influences the budgetary policies of the government.
Tax expenditure is the revenue a government gives up through exemptions, deductions, concessional rates and deferrals in the tax law. It is spending done through the…
Read the model answer →
Q4·10 marks·200 words·Agriculture
Food Security Bill is expected to eliminate hunger and malnutrition in India. Critically discuss various apprehensions in its effective implementation along with the concerns it has generated in WTO.
The National Food Security Bill, enacted in September 2013, converts food from a welfare scheme into a legal right. It covers up to 75% of the rural and 50% of the…
Read the model answer →
Q5·10 marks·200 words·Agriculture
What are the different types of agriculture subsidies given to farmers at the national and at state levels? Critically analyse the agricultural subsidy regime with reference to the distortions created by it.
Indian farm policy since the Green Revolution has relied on cheap inputs and assured output prices to raise production and protect small farmers. The result is a large,…
Read the model answer →

Model answer by the EdiShorts editorial team. It is one well-argued treatment of the question, written to the official word limit — not an official UPSC answer key.